Click to Home
Help Center
Go To Search
Graphic Links
City of Warrenville
28W701 Stafford Place
Warrenville, IL 60555
Ph: 630-393-9427
2018 Landon Avenue Sewer Extension
2018 Landon Avenue Sewer Extension

Project Overview:
 Extension of sanitary sewer from Landon Avenue west to Route 59. 

Approximate Construction Schedule:
July 2018 - Tree clearing and stripping of topsoil
Late July 2018 - Sanitary Sewer installation on east side of project.
August 2018 - Sanitary Sewer installation on west side of project
Late August 2018 - Restoration

Project Status (last updated September 19, 2018):  
Week of July 8: Contractor began tree clearing
Week of July 15: Contractor continued tree clearing and topsoil removal.
End of July/Early August: Contractor began sanitary sewer installation the east section of the project.
Week of August 6: Contractor finished east section work.
Week of August 20: Contractor to begin sanitary sewer installation on the west section of the project. 
Week of August 27 & 3: Contractor to finish sanitary sewer installation on the west section.
Week of September 10& 17: Contract to continue sanitary sewer installation on the east section.

Questions can be directed to Senior Civil Engineer Kristine Hocking at , Deputy Public Works Director Phil Kuchler at or by calling (630) 393-9050.