2019 Road Program
Schedule / Updates

August 15, 2019 Update

Geneva Construction will clean up construction debris and remove unnecessary traffic control devices. Their current schedule includes utilizing a street sweeper will clean the roads and then a liquid prime asphalt coat will be placed on Friday, August 16, 2019, to prepare for paving a layer of asphalt throughout the entire subdivision on Monday, August 19, 2019. 

The electrical subcontractor will continue to work on the street lighting system replacement over the next couple weeks.

Landscape restoration has begun and will continue.

The final asphalt surface coat will not be placed until all other work is complete.

Project completion is expected to occur in mid to late September.



Resident Notices

Below are notices distributed to residents with information about the project:

2019-08-15
2019-08-01
2019-07-26
2019-07-22
2019-07-19
2019-07-16
2019-07-11
2019-07-08
2019-07-05
2019-06-25



Planned Staging of Emerald Green Curb and Gutter Removal and Replacement
Curb and Gutter Staging


Geneva Construction created this exhibit to communicate their approach to curb and gutter removal and replacement. Their approach is to affect only one side of the road in an area at a time, as parking is limited. Vehicles on one side of the street will be able to access their driveways, before the other side loses access to their driveways.




Scope of Work

Emerald Green Subdivision
  • complete removal and replacement of curb and gutter
  • pavement and driveway patching
  • removal and replacement of existing street lights with LED retrofits
  • resurfacing of the roadway

Stafford Place, northeast of Warren Avenue
  • complete removal and replacement of curb and gutter
  • partial removal and replacement of deficient sidewalk
  • pavement patching
  • resurfacing of perpendicular parking areas adjacent to street