Warrenville Road Reconstruction
Schedule / Updates

Week of August 19, 2019
The contractor will perform electrical work, relocating four light poles and installing conduit for new LED stop signs. Landscape restoration is also anticipated for this week. This work may cause minor disruptions to traffic, but the road will remain open throughout this week. 

During the week of August 19, notices will be distributed in door hangers to residents regarding the upcoming August 26 road closure. Access will be maintained to dead end side streets. Mail delivery, garbage pickup, and emergency access will be maintained during that week.

Week of August 26, 2019
Road reconstruction will begin this week.  One way traffic will be maintained from Route 56 east to Mignin at all times.  The road will be closed from Mignin through Behrs Circle Drive West (see Detour map below).  Warrenville Road residents will lose access to their driveways during this time. The contractor will remove the brick pavers, then some of the stone base below the brick pavers, and then will pave the first two layers of asphalt, at which time residents will regain access to their driveways. 

Some side roads may have cross access during this work but residents are urged to use detour routes. Please note that access will be maintained to all dead end side streets.

Week of September 2, 2019 (Labor Day)
The contractor will adjust the structures in the roadway back up to prepare for paving of the last / surface layer of asphalt. The asphalt surface of 4th Street and the areas of Warrenville Road that exist as asphalt, will be milled off. The final layer of asphalt will be paved, and the striping and stamped crosswalks will be completed this week.

Weather is critically important to any construction project, so bad weather could affect the schedule. If there are schedule changes, they will be updated on this page.

Project completion is anticipated in early to mid-September.

Resident Notices

Construction Schedule
2019-07-25 Sched

This was the original construction schedule provided by the contractor. The activities shown for August 19, 2019 and after, have been delayed 1 week.